Bangladesh has reached a unique milestone of power crisis. Since the political change of August 5, 2024, the power sector, like many other sectors of the country, has been in crisis. Apart from political reasons, thousands of factories in the country have closed due to power and fuel crisis. Business establishments have also been victims of disaster.
A song has been released on social media about this, “The country is stagnant during the day, hurricane at night.” It is meant to convey that the country’s economy has come to a standstill, coupled with load shedding. This is not just a song, but a cruel picture of the entire country.
Bangladesh witnessed the highest load shedding in recorded history on Sunday midnight.
At 2 am, there was 3,431 megawatts of load shedding in the country. According to government estimates, the demand for electricity at that time was 16,504 megawatts. The supply was 13,733 megawatts.
On Sunday, the average load shedding throughout the day was 2,000 to 2,500 megawatts. Earlier, in May, there was a load shedding of about 2,500 megawatts across the country. This electricity crisis in the country under the current government has worried those concerned.
It is feared that if the heat increases further, the power situation could go out of control.
Currently, there is some isolated load shedding in some places in Dhaka, which is still at a tolerable level. However, the situation outside Dhaka is quite delicate. Many districts are without electricity for hours.
Industrial and agricultural areas of Mymensingh are without electricity for an average of 12-14 hours a day. There is a cry for electricity all over the country. The government is also considering load shedding in Dhaka to deal with the situation. The Power Division wants to seek the Prime Minister’s permission before load shedding in Dhaka.
However, the Power Minister said that no decision has been taken yet regarding load shedding in Dhaka.
Meanwhile, it has been reported that a decision has been taken to increase gas supply to electricity by reducing gas consumption in fertilizer factories or other sectors. To reduce severe load shedding in the Mymensingh area, orders have been issued to increase electricity production from two plants of United Power Company.
The decision was taken at a meeting held at the Parliament Secretariat on Sunday under the chairmanship of Power Minister Iqbal Hassan Mahmud. The meeting was attended by the State Minister for Power, Energy and Power Secretaries, and various senior officials.
This afternoon, the Power Minister said that one unit of the Rampal power plant is closed due to a mechanical fault. The production in another unit is decreasing. Therefore, load shedding has increased. However, instructions have been given to run the oil-based power plants at full speed.
Following the government’s instructions, a 300-megawatt diesel-based power plant in Khulna has been commissioned to manage the situation.
The Power Development Board (PDB) said that the situation is not being managed due to financial crisis, gas shortage and two coal-based plants not being properly operational.
Apart from this, there is also a lack of coordination between the PDB and the distribution companies. All in all, such a situation has not happened in the electricity sector in the last 5 years.
Robin Barua from the Barai area of Bhaluka, Mymensingh, said that there is no electricity for more than 4-5 hours a day in that area. It is difficult to say when electricity comes at night. In this heat, business and commerce there have completely collapsed due to the lack of electricity. Textile and various agricultural farmers have faced losses.
Gazi Faisal, a resident of the Soap Factory area of Keraniganj, adjacent to the capital, said that there is load shedding there for 8-10 hours every day. His question is, there is no load shedding in the capital. But why is there 8-10 hours of load shedding in the police station next to the capital?
Ranjit Saha from Chandanaish in Chittagong said, “The situation in the area is terrible during the heat. There is almost no electricity. We wait like crows on a pilgrimage for when electricity will come.”
‘Bhaiya card beche’ slogan: 18-hour load shedding a day for 2 months, angry customers block roads
Why is the situation so bad?
The country’s peak hour electricity demand is now more than 18,000 megawatts. But the production is around 14,000. However, the capacity to generate electricity is 29,593 megawatts. So why is electricity not being generated?
In response, PDB officials said that the major obstacle to power generation is the financial crisis. Public and private companies owe PDB 45,000 crore taka in bills. Of this, oil-based power plants in the private sector will receive more than 15,000 crore taka. They owe PDB 7-8 months of bills.
Bangladesh Private Power Producers Association (BIPPA) President David Hasnat said that private companies want to help the government to make the country free from load shedding. But for this, they have to pay the outstanding electricity bills. If they do not get the outstanding money, how will the companies buy oil for the power plants?
The PDB said that there are 43 large and small furnace oil-based power plants in the government and private sectors in the country. Of these, Digital Power’s 102 MW, Desh Energy Chandpur’s 200 MW, Tangail’s 22 MW, and Orion Khulna’s 105 MW plants do not have even a liter of oil in stock.
Besides, 3 tons of furnace oil is stored at Raj Lanka Power Plant in Natore, 74 tons at EPV’s Thakurgaon 115 MW plant, 98 tons at North-West Power’s Mollar Hat power plant, 6 tons at Comilla 52 MW plant, 39 tons at Feni 114 MW plant, and 32 tons at Orion Meghnaghat plant. With which the power plants cannot be operated. Most of the remaining plants do not have more than 10 to 15 days of oil stored.
Load shedding and ghost bills: Impatient mob ties rural electricity worker to pole, beats him up
Apart from this, out of the 10 oil-based power plants of PDB, only Shantahar power plant has enough oil to operate for 10 days. The rest have enough oil to operate for 1 to 8 days. In this situation, although the furnace oil-based power plant has a capacity to generate 5,641 megawatts of electricity, only 1,03 megawatts are currently being generated (at 11 am on Sunday).
It is learned that United Group has two oil-based plants of 200 and 150 MW in Mymensingh. Due to outstanding bills, only 100 to 150 MW of electricity is available from those two plants. Now the Power Minister has urged them to pay their dues and increase power production. United PDB has an outstanding debt of Tk 4,000 crore.
The country has a capacity to generate 6,927 megawatts of electricity from coal-fired power plants. But the second unit of the Rampal power plant is closed due to tube problems. The remaining units are also generating 400 megawatts, while the capacity is 600 megawatts.
The Norenko coal-based plant is supposed to produce more than 1,200 megawatts. But it is not able to produce more than 1,000 megawatts. S Alam Group’s SS Power is supposed to provide more than 1,200 megawatts of electricity. But due to outstanding bills and their various demands, the plant is not always running at full capacity.
In total, about 5,000 megawatts are available from coal-fired plants.
The gas-based power plant has a power generation capacity of 12,472 megawatts. But on Sunday at 11 am, only 5,111 megawatts were produced. In other years, the gas allocation for the power plant was from 1.2 billion cubic feet to 1 billion cubic feet. Now, 915 million cubic feet is being provided.
It is learned that in Sunday’s meeting, it was ordered to provide at least 1 billion cubic feet of gas to the power sector to reduce load shedding.
The Energy Department says that 60 percent of the country’s gas production is used in the power sector, including captives. This is harmful to the country. Because various sectors, including industry, are sinking due to the gas crisis.