Special Report
An important part of the economic cooperation between Bangladesh and India is the Line of Credit (LoC) scheme provided by India. Since 2010, India has provided a total of US$ 7.5 billion in credit facilities to Bangladesh through these three LoC agreements, which are mainly being used for infrastructure development, railways, roads, power, shipping and investment in the social sector.
These loans carry an interest rate of just 1 percent and are repayable over a 20-year period with a 5-year grace period. However, the pace of disbursement has been slow due to delays in project implementation, high bids from Indian contractors, terms of importing materials (75% from India), and complex approvals.
A total of $1.88 billion has been disbursed as of October 2025, which is about 25% of the total debt.
A total of over 40 projects have been taken up under these LOCs, of which 15 are completed, 8 are ongoing and the rest are in preparation or tender stage. Work on some projects has been halted due to recent political unrest (following the 2024 agitation) and security concerns of contractors.
Below is a detailed list of these projects in bullet form, including the date of acceptance (at the time of contract or DPP approval), completion date, current status, sector, and estimated cost.
(Information sources are collected from sources such as Economic Relations Division (ERD), Prothom Alo, and Business Standard.)
Brief history of the LoC agreement
First LoC ($862 million): Signed on 7 August 2010. Mainly spent on rail and road sectors. Disbursement of $770 million (90%).
Second LoC ($2 billion): Signed on 9 March 2016. Includes power, rail, road, ICT, health and professional education sectors. $520 million has been released.
Third LoC ($4.5 billion): Signed on 4 October 2017. Focuses on rail, road, power, shipping and infrastructure development. $550 million has been released.
List of projects: accepted, completed and ongoing
Under the first LoC (15 projects undertaken, 12 completed):
| Serial | Project name | Project acceptance | Completion date | Sector | Expenditure ( million $) | Status |
| 1 | Construction of Khulna – Mongla railway line | 2011 | 2026 (unofficially completed, officially pending) |
Rail | 500 million dollars | Trending |
| 2 | Sirajganj – Ahsanullah School Rail Line | 2012 | 2018 | Rail | $120 million | Completed |
| 3 | Tongi – Joydevpur Railway Line ( Third and Fourth Tracks ) | 2013 | By 2025 | Rail | $334 million | Trending |
| 4 | Development of Palashi – Jhenaidah Railway | 2010 | 2017 | Rail | 80 million dollars | Completed |
| 5-12 | Various small rail and road projects ( e.g. Bogra – Shema Rail , Rupsha – Khulna Road ) | 2010-13 | 2015-2020 | Rail/Road | 200 million dollars | Completed |
Under the second LoC (15 projects undertaken, 3 completed):
| Serial | Project name | Project acceptance | Completion date | Sector | Expenditure ( million $) | Status |
| 13 | Ashuganj – Akhaura road expansion | 2016 | 2024 (closed, due to political reasons) |
Road | $120 million | Trending |
| 14 | Acura – Agartala Rail Connection ( Bangladesh Part ) : | 2016 | 2023 (grant portion completed) |
Rail | $48 million | Completed |
| 15 | 49 polytechnic institutes upgraded | 2017 | 2021 | Education | $114 million | Completed |
| 16 | Modernization of two teachers training institutes | 2017 | 2020 | Education | 30 million dollars | Completed |
| 17 | Establishment of medical colleges and hospitals | 2016 | 2026 | Health | $150 million | Trending |
| 18-22 | Power development and ICT projects ( e.g. Rooppur Substation ) | 2016-2018 | 2019-2022 | Electricity/ICT | 300 million dollars | Completed/In Progress |
Under the third LoC (16 projects undertaken, 1 completed):
| Serial | Project name | Project acceptance | Completion date | Sector | Expenditure ( million $) | Status |
| 23 | Khulna – Mongla Railway Line ( Signaling and Telecom ) | 2018 | 2025 | Rail | $150 million | Trending |
| 24 | Feni – Anantagarh railway line | 2018 | 2026 | Rail | $250 million | Trending |
| 25 | Bangabandhu Sheikh Mujib Rail Bridge | 2018 | 2022 | Rail | 180 million dollars | Completed |
| 26 | Bay Terminal , Chittagong | 2019 | Cancelled (dropped in 2023) | Shipping | 400 million dollars | Cancel |
| 27 | Syedpur Airport Modernization | 2019 | Cancelled (removed in 2025) | Transportation | $370 million | Cancel |
| 28 | Bangabandhu Sheikh Mujib Industrial City | 2018 | Cancelled (in preparation) | Art | $160 million | Cancel |
| 29-32 | Various rail and power projects (e.g. Dhaka-Chittagong Highway, solar plants) | 2018-20 | Ongoing/Preparation | Road/Electricity | 500 million dollars | Trending |
Cancelled Projects: Decision Process
A total of 11-12 projects under the LoC have been cancelled or dropped in the last few years, mainly due to lengthy processes, cost escalation, contractor reluctance and political instability. These decisions were not taken by Bangladesh alone; rather, they were taken through India-Bangladesh joint committees (e.g. Joint Working Group or Line of Credit Review Meeting). For example, in the March 2024 review meeting, the two countries jointly decided to drop unacceptable projects from the LoC.
Similarly, in the March 2025 meeting, 11 projects were proposed for cancellation, which were reviewed by a joint technical committee (ERD, Indian High Commission, Exim Bank and representatives from the implementing agencies). This committee determined the exit strategy for the projects, so that even if the projects are cancelled, there is an opportunity for alternative funding.
Below is a list of the major projects cancelled in bullet points, along with the decision process:
Bay Terminal, Chittagong:
LOC No. 3, adopted 2019, cancelled in 2023, sector shipping, cost $400 million; dropped due to lengthy process at Joint Review Meeting (2023).
Modernization of Syedpur Airport:
LOC No. 3, adopted 2019, cancelled in 2025, Sector Transport, cost $370 million; cancelled in March 2025 due to cost escalation and contractor reluctance at the Joint Committee.
Bangabandhu Sheikh Mujib Industrial City:
LOC No. 3, adopted 2018, cancelled in preparation stage (2024-25), sector industry, cost $160 million; cancelled due to non-acceptance at the Joint Working Group Meeting (April 2024).
Mirsarai and Mongla Indian Economic Zone:
LOC No. 3, adopted 2015 (MOU), cancelled October 2025, sector Industrial, cost $600 million (total); jointly delisted or removed from the list at the review meeting in March 2024, as only 1% of the cost was incurred and Indian contractors did not tender.
Solar Based Stations for Strengthening Teletalk Network:
LOC No. 2, adopted 2018, cancelled May 2023, sector ICT, cost $30 million; jointly excluded with the consent of the Indian authorities, due to high cost of equipment.
Supply Machinery for Solid Waste Management:
LOC No. 2, adopted 2018, cancelled May 2023, sector environment, cost $24.83 million; cancelled by mutual consent, due to high cost.
Khulna-Mongla Rail Project WD-3 Package (Signaling):
LOC No. 1, adopted 2018, cancelled March 2022, sector Railways, cost $50 million; dropped due to delay in joint review.
Jamalpur Medical College and Hospital:
LOC No. 2, adopted 2017, cancelled March 2022, sector health, cost $40 million; cancelled due to implementation challenges in the Joint Committee.
Two packages of Rooppur Power Transmission Line:
LOC No. 2, adopted 2017, cancelled March 2022, sector Power, cost $113 million (total); jointly excluded, due to cost and delay.
Mongla Port Upgrade:
LOC No. 3, accepted 2020, cancelled October 2025, sector shipping, cost $388 million; cancelled in joint committee due to political unrest and contractor reluctance.
Khulna-Darshana railway line:
LOC No. 1, adopted 2018, cancelled March 2025, sector Railway, cost $312 million; cancelled due to lack of additional funding at joint review meeting.
Parbatipur-Kauniya railway line:
LOC No. 1, adopted 2018, cancelled March 2025, sector Railway, cost $120 million; dropped due to cost escalation in joint committee.
Notable achievements of completed projects
Twelve projects have been completed under the first LoC, which have improved rail connectivity. For example, the Sirajganj-Ahsanullah line (completed in 2018) has enhanced commercial connectivity. The upgrade of 49 polytechnics in the second LoC (2021) has strengthened vocational education, benefiting over 50,000 students. The most notable one is the Bangabandhu Sheikh Mujib Rail Bridge (2022) in the third LoC, which has facilitated rail connectivity by crossing the Yamuna River.
A total of 15 completed projects have resulted in $2 billion in investment in Bangladesh’s infrastructure, boosting trade and employment.
Of the 8 ongoing projects, the Khulna-Mongla rail line (running since 2011, delayed by 15 years) is the largest. The work is delayed due to 57% higher bids in the tender. The Ashuganj-Akhaura road (since 2016) is closed in 2024 due to political unrest.
In 2025, 11 projects (such as Syedpur Workshop, Mongla Economic Zone) have been cancelled through the joint committee, which will bring down the total LOC amount to 4.68 billion. A total of 6 projects have been jointly dropped in the last 3 years.
Regular review meetings between ERD and India (last in March 2025) are emphasizing on accelerating the disbursement of funds. Bangladesh is seeking project-based grace periods and flexibility in contractor selection. While this LoC will strengthen Bangladesh’s infrastructure, more bilateral cooperation is needed to enhance efficiency.