The Power Development Board (PDB) is unable to generate electricity as per the demand. Power load shedding is increasing in line with the heat. Although the government has said that there has been a load shedding of 2,000 megawatts for the past few days, in reality, multiple sources from power distribution companies have reported a power shortage of more than 3,500 megawatts. The highest load shedding of the current season occurred on Wednesday due to a decrease in the production of a large power plant.

Meanwhile, life is being disrupted across the country due to the lack of electricity. Everything that depends on electricity, including business, medicine, education, is at a standstill. No village or city is left behind. Load shedding is increasing in tandem.

According to the Power Grid Company (PGCB), the power shortage was around 2,500 megawatts on Wednesday afternoon. However, various sources said the load shedding was more than 4,000 megawatts yesterday. At 12 noon on Wednesday, the power shortage at the Rural Electrification Board (REB) was more than 3,000 megawatts.

At that time, the PGCB website showed load shedding of 2,495 MW by six distribution companies. However, there have been allegations that the government is hiding the load shedding. The real reality is not being communicated to the public.

PDB member (production) Zahurul Islam said, “Production has stopped from one of Adani’s units. To deal with the situation, power generation from oil-fired plants is being increased. Even then, it is not possible to manage it.”

It is learnt that a warning signal was received from the bearings of one of the power plant units after midnight on Tuesday. After that, production in that unit was stopped. It has been informed that it may take three to four days to repair it.

On Tuesday night, 1,497 megawatts of electricity was available from Adani, but at 2 am, it dropped to 764 megawatts. On Wednesday night, 746 megawatts of electricity came from Adani.

Concerned people said that Adani’s reduction in supply has caused a serious deterioration in the power situation in Rajshahi and Rangpur regions. In some places, load shedding has reached 15-16 hours. People have become restless. Especially SSC examinees are unable to study.

The PDB said that the peak demand for electricity during the day on Wednesday reached 15,690 megawatts. Due to the gap between production and demand, about 2,500 megawatts had to be provided for load shedding during this time. This increased further during the peak demand at night.

PGCB had estimated the peak demand for electricity for Wednesday night at 16,700 MW. On Tuesday night, at 9 pm, the peak demand for electricity reached 16,550 MW. At that time, the production was 14,623 MW. The deficit was 1,840 MW. In this way, the deficit is decreasing every day. This is increasing load shedding.

Of the country’s 136 power plants, 13 are out of production due to gas shortage, 9 due to fuel oil shortage, and 8 are out of production for maintenance work. The current capacity of electricity generation from gas is 12,200 megawatts.

Due to the gas shortage, more than 5,200 MW cannot be generated from there. Although the electricity demand has exceeded 16,000 MW at the beginning of the summer, the total generation is only 13,000 to 14,000 MW. As a result, regular load shedding is being done to meet the shortage. The load shedding rate is increasing every day.

Load shedding has increased not only in the capital but across the country.

On Wednesday, there were reports of multiple load shedding in different areas of the capital. The situation outside the capital was dire. Starting from neighboring Gazipur, Kushtia, Natore, Noakhali, Rajbari, Faridpur and other districts, public life has been disrupted due to power shortage.

The Electricity Department has said that load shedding is being carried out day and night as supply is half or less than demand. The load shedding in the industrial area of ​​Gazipur has affected production.

Production is being severely disrupted due to frequent power outages in about 5,000 factories in various areas including Tongi, Konabari, Kaliakoir. Patients and exam candidates are in trouble.

Only one-third of the electricity demand is being supplied from Kumarkhali in Kushtia. Against the demand of 16-18 megawatts, only five to seven megawatts are being supplied.

Load shedding is happening four to five times a day in Natore. Although the demand in the evening is 153 MW, the supply is 93 MW. Students, small businessmen and people in the transport sector are the most affected. In Lalpur in the same district, there is no electricity for about 16 hours out of 24 hours.