❐ Local correspondent
There have been allegations of widespread irregularities in the repair work of a road built for 6.8 million taka in Bauphal upazila of Patuakhali. Less than a month after the construction work was completed, the carpeting has come off at various places on the road, creating deep potholes.
Residents have been distressed by this and have demanded a proper investigation into the incident and action against those responsible, alleging a waste of government money.
According to sources from the Local Government Engineering Department (LGED), an initiative was taken to renovate the damaged section of the Naumala-Baufal road in the Upazila Sadar Union from Olipura Bazar to the municipality’s Howlader Bari in the 2025-26 fiscal year. A contracting company named Toufiq Trade International won the work for 68 lakh taka through a tender.
Locals allege that the carpeting work was completed in a hurry with tack coat within just seven days of receiving the work order. They also allege that the specifications or schedule set for the construction work were not followed. As a result, just 25 days after the work was completed, the carpeting has come off at various places on the road, creating large potholes.
The residents further claim that low-quality materials were used in the construction work. They also alleged that a large amount of bitumen and sealcoat was taken back from the site without being used after the work was completed.
They say that due to these reasons, the road has become unusable in a short time.
Locals have demanded that necessary action be taken against those involved in the incident, alleging corruption and irregularities in government development projects.
According to local sources, the construction of the road was implemented by Md. Kamruzzaman alias Kamrul Hawlader, a member of Baufal Upazila BNP and former general secretary of Baufal Sadar Union BNP, as a subcontractor from the main contractor, Toufiq Trade International.
However, Kamruzzaman has denied the allegations against him.
He said that a group is spreading propaganda against him for political purposes ahead of the upcoming elections.
He claimed that the construction work has been completed as per the schedule. If there are any defects, immediate steps will be taken to repair them.
On the other hand, Ali Ibne Abbas, Deputy Assistant Engineer of Baufal LGED, who is in charge of supervising the project, said that the carpeting of the road may come off due to continuous rains. The damaged parts will be inspected, and necessary repairs will be taken immediately.
The real picture will come out if the locals’ complaints, quality of work,k and implementation process are investigated impartially. Therefore, they have demanded that necessary action be taken against those responsible after verifying the quality of this project implemented with government funds.