Tk 280 Crore Road Now Lies Like a Ploughed Field After Contractor’s Work Order Cancelled Over ‘Awami League Links’

September 25, 2026 • National
Tk 280 Crore Road Now Lies Like a Ploughed Field After Contractor’s Work Order Cancelled Over ‘Awami League Links’
Share this News

 ❐ BD Digest Desk


You have to cross the Khanjahan Ali Bridge built on the Rupsa River and enter Khulna metropolis via the northern connection road. However, the scenery changes a little after moving a little from the bridge. Although there is bitumen carpeting at the beginning, you have to stop after about 100 yards. There is no bitumen in the middle of the road, about 50 to 60 feet, and there is no sign of bricks. As the trucks move over the clay, the place looks like a newly cultivated field.

This is the current view of the Rupsha Bridge connection section of Khulna city’s important shipyard road. This road is one of the main routes for millions of people in the Mathabhanga area, including hundreds of sawmills, rice mills, rice husk mills, sand pits, SRB-6 headquarters, the Navy training base Solam, and Riverview Park in the Rupsha and Luantchara areas.

The road has been in a dilapidated condition for more than a decade. The Khulna Development Authority (KDA) took up the project to widen it in 2013. But even after 13 years, the project has not been completed. The suffering of the people has not diminished. The project was taken up during the Awami League government. But after the political change of August 5, 2024, the work orders of the contractors in charge were cancelled out of revenge on charges of ‘Awami involvement’.

Construction of the road has been completely halted for the past year due to complications related to contractor cancellation. A July 2026 report stated that work on the 3.778-kilometer section of the road had been stalled for 10 months.

This reporter was around the road from 10:50 am to 1 pm on Tuesday. At that time, the salt marsh was seen passing through muddy areas like ‘grass fields’, stagnant ‘ponds’ and numerous small and large holes. In some places, local people have tried to temporarily fill the holes by throwing pieces of bricks. This has made the situation even more precarious. Vehicles are having to sway while moving through that section.

The contractor had laid bricks and stones at various places to reconstruct the road. But as the rainwater washed them away, holes were formed in several places. Later, due to the movement of vehicles, those holes gradually got bigger. In the meantime, with the onset of monsoon, many holes were submerged in water and took the form of sinkholes. It was not possible to count the number of such sinkholes on the entire road.

It took this reporter 29 minutes to cover the 3.778-kilometer road on an easy bike, avoiding high places, low places, and potholes. After such a long jolt, the condition of his waist also became deplorable.

When asked about this at a tea shop next to the Dada Match Mill Mosque near Rupsa, rice mill worker Azibar Rahman said, “Can’t you do the cleaning in one day? And I have to go back and forth every five days. My life goes out every time I come and go.”

As it became risky to ride an easy bike on some parts of the road, this reporter went under the bridge to the other side. There, the situation was even more dire. A huge hole had formed on the road, about 70 to 80 feet wide. From a distance, it looked like a pond. Measuring the depth with a stick, it was seen that the hole was about 17 inches deep.

Work not completed, costs increased

A project worth Tk 98 crore was approved on May 7, 2013, to widen the road to four lanes and reconstruct it. After a long nine years, on January 12, 2022, KDA awarded the work order to Ataur Rahman Limited and Mahabub Brothers Private Limited (a joint venture). The contractor started construction on January 20 of that year. According to the contract, the work was supposed to be completed by June 2024.

But on August 7, 2025, the contract with the contractor was canceled due to allegations of ‘public involvement’. Since then, construction of the road has been suspended.

Although the road is not completed, the cost of the project has increased in several stages. The cost was increased to Tk 259 crore during the first revision of the project in 2020. Later, in 2026, the cost was revised again and set at Tk 280 crore. In June, an ECNEC meeting ordered an investigation to find out the reasons for the delay in the project. According to the published report, the initial project cost of about Tk 99 crore stood at Tk 254 crore after several revisions.

An investigation was ordered to find out the reason why the project was not completed even after 13 years. Later, the investigation committee of the Ministry of Housing and Public Works submitted its report on August 31. The report recommended departmental punishment for 14 people.

The suffering did not stop even after public protests.

Local businessmen and residents have formed human chains at least eight times in the past decade to demand the repair of Shipyard Road. In addition to submitting memorandums to ministers and advisors, they have also held various programs, including besieging the Khulna Development Authority (KDA) office. But despite these programs, the road’s dire condition has not been permanently resolved.

While inspecting the road, it was learned from talking to local residents that there are 10 educational institutions on both sides of the nearly four-kilometer-long Shipyard Road. Once, there were 27 rice mills and 250 wood chip mills in the vicinity. There were more than 450 businesses in the Bandabazar area.

Traders say that their business has suffered a major loss due to the poor condition of the roads. 21 rice mills have closed in the past decade due to various reasons including difficulties in transporting goods. Traders are facing losses of more than 100 crore taka annually. Sales of timber traders have also fallen by less than half. Almost half of the sawmills have already closed.

Kazi Selim Ahmed, president of the Timber Traders Association, said, “We cannot be said to be at a loss. Sales have decreased. More than half of the traders are now destitute.”

Waiting for new contractor to be hired

KDA Chairman Shafiqul Alam Mona said, “The approach part of Rupsha Bridge will have to be built with concrete. Due to this, the cost of the project has increased. A new contractor cannot be appointed until the project gets approval from ECNEC.”

He said that the process of taking action against the accused has been initiated on the instructions of the Prime Minister. He hopes that the revised project will be approved in the next ECNEC meeting. After that, it will be possible to quickly appoint a new contractor and complete the road work by next year.

An investigation into the project’s delay was ordered at an ECNEC meeting on June 9, 2026. In that meeting, Prime Minister Tarique Rahman ordered to find out the reason why the project had not been implemented for almost 13 years.

Meanwhile, Jahangir Hussain Helal, MP for Khulna-2 (Sadar-Sonadanga) constituency, has demanded the speedy renovation of the road in the National Parliament twice in the last six months. However, even then, there has been no visible progress in the construction work.

MP Helal said, “I have to return home through that road. I understand the suffering of the people. I can’t explain it to others.”


Source: Daily Samakal

 