Who Benefits as Chinese Power Costs Rise From Tk18 per Unit Under Hasina to Tk25?

August 27, 2026 • Economy, National
Who Benefits as Chinese Power Costs Rise From Tk18 per Unit Under Hasina to Tk25?
Share this News

Staff Correspondent

The dollar-based electricity price set about five years ago for the waste-to-energy project in Dhaka’s Aminbazar remains unchanged. But at the exchange rate at that time, the price per unit of electricity was 18 taka 295 paisa, now Bangladesh will have to pay about 25 taka at the current exchange rate for the same price of 21.78 US cents.

In other words, the Chinese company China Machinery Engineering Corporation (CMEC) is not demanding more dollars. But after a long delay in the implementation of the project, the price of electricity in Bangladeshi currency is increasing by about 37 percent due to the conversion of the old dollar tariff to the current exchange rate.

Now the question arises, when the project was on the verge of being finalized in 2021, why was the dollar rate, which was considered to be equivalent to 18 taka 295 paisa, not revalued a few years later during the implementation of the project? Rather, why is the burden of additional costs being imposed on Bangladesh by calculating the old dollar rate at the current high exchange rate?

The bigger question is, after such a long delay in project implementation, has the government made any attempt to reduce tariffs, share exchange rate risks, or renegotiate financial terms with Chinese companies?

There is no clear answer to this question from public information so far.

18 taka to 25 taka calculation: The proposal for a 42.5 MW waste-to-energy project in Aminbazar received government procurement approval in November 2020. At that time, the Bangladesh Power Development Board was informed to purchase electricity at a rate of 21.78 US cents per unit, or the equivalent of 18.295 taka, for 25 years.

Later, Chinese state-owned enterprise CMEC was retained as the project sponsor. The project was to be implemented on a build-own-operate (BOO) basis. Dhaka North City Corporation would provide the land and waste, and CMEC would set up the power plant.

In August 2021, the draft PPA also revealed a price of 21.78 cents or 18.295 taka per unit.

That is, the tariff was originally set in dollars. 18 taka 295 paisa was its taka-based equivalent at the exchange rate at that time.

Now the dollar is much more expensive than before. As a result, if the same 21.78 cents is converted into taka at the current exchange rate, the taka figure comes to about 25 taka.

So the question here is not directly ‘did the Chinese company increase the price’. Rather, the question is, why is the Bangladesh government deciding to implement the old dollar tariff at the current exchange rate, while not trying to reconsider the tariff after the long delay of the project?

Complaint about the interests of the minister’s son:

In addition to questions about the financial terms of this project, there is also a discussion of allegations in the political and social arena surrounding the name of Abed Hasan Mahmud, the son of Power Minister Iqbal Hasan Mahmud Tuku.

The allegation is that he is playing a role in helping the Chinese company benefit from the project through financial transactions.

Rather, the question has become more important in the Aminbazar project, because for the same project, the same Chinese company, and the same dollar-based tariff, the cost in Bangladeshi taka has increased from about 18 taka to 25 taka in a few years.

Although the project approval and contracting process progressed in 2020-21, production did not start on time. As a result, the time by which Bangladesh was supposed to get electricity along with waste management has passed.

During this long period, Bangladesh’s economy has undergone major changes. One of the most important changes is the massive depreciation of the taka against the dollar.

The consequences of this are directly affecting this project.

According to the 2020-21 calculations, where the taka equivalent per unit was 18.295 taka, at the current exchange rate it is about 25 taka. This means that the financial impact of the depreciation of the taka during the delay in project implementation is now being added to the cost of purchasing electricity.

Why wasn’t the price revised?

Not only has the dollar exchange rate changed since 2021. The financial situation of the power sector, foreign exchange markets, technology, construction costs, and the international financing environment have also changed.

Even so, efforts are being made to finalize the project while maintaining the old dollar tariff.

If the government says that 21.78 cents is the fixed tariff in the agreement and there is no scope for changing it, then it is necessary to disclose which clause of the agreement has closed the scope for tariff revision.

And if there is an opportunity to re-set the price, then why wasn’t that opportunity used is also a question.

Because if the main purpose of the project is cost-effective waste management and power generation for the benefit of the people, then it was natural to try to make the financial terms more favorable for Bangladesh after several years of delay in project implementation.

But according to public information, no such negotiation has been reported so far.

Visited 113 times, 1 visit(s) today