Yunus government is buying LNG worth Tk 1 lakh crore from Peter Hass’ company at an additional cost

September 11, 2025 • Economy, International, National
Yunus government is buying LNG worth Tk 1 lakh crore from Peter Hass’ company at an additional cost
Share this News

❐ Special Correspondent

The Yunus government has signed a long-term energy deal in the name of reducing the Bangladesh-US trade deficit. Under this deal, US company Accelerate Energy will supply LNG (liquefied natural gas) worth more than Tk 1 lakh crore to Bangladesh in phases over the next 15 years.

Bangladesh’s relationship with Accelerate Energy came into the spotlight thanks to former US Ambassador Peter D. Haas. After completing his stint as ambassador in Dhaka, he joined the company as a strategic advisor. Since then, the company’s business in Bangladesh has been expanding rapidly.

Peter Haas is a hot topic in the political arena of Bangladesh. Peter Haas was always in the news for various reasons during his time as ambassador to Bangladesh. During his two years as the US ambassador in Dhaka, Peter D. Haas was vocal about the country’s human rights, media freedom, and the role of civil society, as well as the issue of a fair and inclusive election.

Before joining the multinational company Accelerate Energy, he served as the US ambassador to Bangladesh. He took over as the embassy in Dhaka in March 2022. He left the service on July 23, 2024. He returned to the United States just days before the July-August terrorist attacks of last year, completing his term and retiring from the Foreign Service on September 27. But his work in Bangladesh was not over yet. Just three days later, on October 1, he joined Accelerate Energy, a US multinational company that exports liquefied natural gas (LNG) and has investments in Bangladesh.

Agreement under criticism

Criticism began after a new LNG supply deal was signed with Accelerate Energy during the Yunus government. There were allegations that the contract was awarded at a relatively high price, excluding other competing companies in an international tender.

As per the agreement, the government approved the import of LNG from Accelerate Energy in November last year. Then on January 8, 2025, Petrobangla approved the proposal to import 3.36 million MMBTU of LNG from the United States. The total cost of this is estimated at Tk 752 crore. The price per MMBTU is estimated at $15.69, which is an average of $2.5 higher than the international market price.

Former US Ambassador and current advisor to Accelerate Energy, Peter D. Haas, returned to Bangladesh earlier this month. After arriving in the country, he first visited the company’s floating LNG terminal (FSRU) in Maheshkhali, Cox’s Bazar. Then, on September 3, he met with Foreign Secretary Asad Alam Siam. The meeting discussed Accelerate Energy’s role in increasing gas supply to Bangladesh and its future plans.

Read: Peter Haas in Cox’s Bazar again

15-year supply contract

According to government data, under this long-term agreement with Accelerate Energy, the company will supply LNG worth $8.5 billion (approximately Tk 14,550 crore at Tk 123 per dollar) over the next 15 years. During this period, 232 cargoes of LNG will arrive in Bangladesh. Not only that, it has also been decided to give priority to Accelerate Energy in purchasing LNG from the international market.

The US company will also be given priority in purchasing LNG from the international spot market. Apart from this, the government is also considering importing other products in this sector, especially diesel, from the US to reduce the trade deficit. The concerned officials of the Energy and Mineral Resources Department gave this information. The concerned officials of the Energy and Mineral Resources Department confirmed this information.

Engineer Md. Shah Alam, General Manager (LNG Division) of Transformed Natural Gas Company Limited (RPGCL), said, “The government is emphasizing on importing LNG to reduce the country’s gas crisis. As part of this, a long-term agreement has been signed with a US company.”

On the other hand, a Foreign Ministry official said that during the counter-tariff negotiations with the United States last July, Bangladesh agreed in principle to buy more American products. In this context, how to increase LNG imports from American companies like Accelerate Energy in the future was also discussed in the meeting between the Foreign Secretary and Peter Haas. This plan is also mentioned in the policy paper sent by the Ministry of Energy to the Ministry of Finance.

The agreement was signed on November 23, 2023, during the Awami League government and under the special provisions of the power and energy sector. Dr. Yunus’ interim government did not cancel several agreements under the special provisions of the power and energy sector after taking power. The reason claimed was that since it was a final agreement with the American company, it could not be canceled due to legal obligations.

However, energy experts say otherwise. Some experts, on condition of anonymity, said that although the opposition spread misinformation about the agreements made during the Awami League government, the agreements were actually profitable for Bangladesh. The Yunus government did not want to cancel these agreements because it could not find an excuse to cancel them. Moreover, there are obligations in the G2G agreement. So that the agreement remains intact even if the government changes. But there is no such clause in the agreement with the private company.

According to the agreement, Peter Hass’s Accelerate Energy will supply LNG to Bangladesh until 2040. An average of 0.85 to 1 million tonnes (MTPA) of LNG will be imported each year. Of this, 28 cargoes will arrive in 2026-27. Then 16 cargoes will arrive each year from 2028 to 2040. The average annual cost under this agreement will be about $600 million.

In addition to this long-term contract, Accelerate is also supplying LNG from the spot market. They have already supplied 16 cargoes worth approximately $637 million. There is also the potential to supply spot cargoes worth over $200 million per year through open tenders in the future.

Dhaka plans to reduce customs deficit

The policy paper titled “Potential of Energy Imports to Address the Bangladesh-US Trade Imbalance” states that the biggest opportunity to rapidly increase purchases to reduce the tariff deficit lies in the energy sector. In particular, LNG and petroleum products (crude oil, refined oil, LPG, etc.) are the mainstays of this sector.

Key recommendations of the policy paper

The policy paper contains several proposals:

  • Including US refineries in the planned annual import of 3.8 million tons of fuel oil.
  • Going through a long-term contract or tender process for diesel and fuel oil from US Gulf Coast refineries.
  • Ensuring at least 0.2 million tons of US diesel imports per year (about $100 million), which would be extremely beneficial for Bangladesh.
  • Initiating new LPG contracts through tenders with US suppliers to meet growing LPG demand.

 

Special

Press Secretary Shafiqul Alam claimed at a press conference that Petrobangla signed this Tk 1 lakh crore agreement with Accelerate Energy on November 7, 2023. However, this is completely misleading information.

There has been no such deal to buy LNG worth Tk 1 lakh crore in 15 years. In the energy sector or any other sector, long-term business agreements do not mention the price of the product. The price of any product does not remain constant for 15 years. The exchange rate of currencies is also variable. The purchase and sale agreement signed with Accelerate Energy states that Petrobangla will buy 0.85 to 1 million tons of LNG per year, starting in January 2026. Accelerate Energy will supply 0.85 million tons of LNG in 2026 and 2027. It will supply 1 million tons per year from 2028 to 2041.

The contract also includes how the price of LNG will be determined. It will be determined here in the same way that other types of fuel are priced. The market price at the time of delivery is usually lower than the price in a long-term contract.

The day after the agreement was signed on November 7, 2023, Accelerate Energy filed a notice with the New York Stock Exchange on November 8. Accelerate Energy is a publicly traded company on the New York Stock Exchange. They informed their shareholders of this information. After the news was released on November 8, their share price rose from $15 to $18. Today, Accelerate’s share price is $23.70.

This means that the issue of purchasing gas worth 1 lakh crore taka in 15 years is confusing. It is now impossible to understand where the money will end up after 15 years.