Special Correspondent
According to official data from the Power Department and Power Cell, the current installed power capacity in Bangladesh is 32,322 MW (some sources mention 28,919 MW or 28,616 MW, including imports).
According to the latest data (February 2026), the demand is close to 13,000 MW, and the Department of Power estimates that this year’s demand could peak at 18,000 MW.
The record for the highest electricity generation on April 19, 2024, was 15,648 MW, which was broken on July 23, 2025, to set a new record for the highest generation, 16,794 MW.
Currently, full capacity is not being utilized due to fuel (gas, coal, oil) shortages and arrears—about 40-60% of power plants are idle or partially operational. Capacity is much higher than demand, but actual production remains close to or below demand due to fuel shortages, arrears, and economic reasons.
Minister of Power, Energy and Mineral Resources Iqbal Hassan Mahmud Tuku said that efforts are being made to ensure uninterrupted power supply in this situation.
He admitted that there is ‘chaos’ in the power and energy sectors – there are power plants but no fuel, huge arrears are piling up. The capacity charges for the plants are being paid while they are being installed.
Talking to reporters of Energy Bit in the ministry’s meeting room on Thursday, the minister said, “We are trying to ensure uninterrupted power supply. We are looking for solutions and making plans to overcome the crisis.”
He also said,
“The BNP government (2001-2006) did not impose the burden of debt on the people even though they allowed load shedding. Now the lights are on, but the nation is drowning in debt. “It is better to suffer than to take the burden of debt.”
In the context of this statement, the question arises – where capacity is much greater than demand (almost more than 100% reserve capacity), why is the management of regular fuel (coal, gas, oil) supply being disrupted?
During the previous Awami League government, electricity capacity was rapidly increased and energy security was ensured, but all of that collapsed due to the mismanagement of the Yunus government.
At the end of Yunus’s interim government (as of February 2026), the total outstanding bills in the power sector were mentioned at Tk 45,000 crore (some sources up to Tk 47,000 crore). The new Power Minister Iqbal Hassan Mahmud Tuku mentioned this figure. Of these:
- BPDB owes about 20,000 crore to private power producers (IPPs).
- Gas supply companies owe around 7,000 crore taka
- The rest is due to foreign companies, including Adani.
Overall, domestic and foreign companies owe Tk 45,000 crore, which has brought the power sector to a “bankruptcy situation”. The Awami League government left behind arrears of Tk 39,000 crore, which was in the process of regular supply and settlement. The arrears were paid to the power companies in phases every 3 months.
Of these, Adani Power had the highest arrears, yet Adani never stopped supplying power due to arrears. The arrears with local private power producers (IPPs) were lower at that time.
During the interim government’s tenure, foreign debt (such as to Adani) has been largely reduced, but arrears to local private producers have increased. The reasons cited for this include the fuel crisis, pressure to reduce subsidies, revenue shortfalls, and payment delays. The current government is now planning to pay off the arrears, but the fiscal crisis in the revenue sector remains deep.
The question remains whether this mismanagement by the Yunus government is a deliberate negligence, a result of economic pressure, or a planned attempt to shift the blame onto the Awami League government. Otherwise, why would the power sector, which was the most capable sector in Bangladesh, go bankrupt in just 18 months?
The current government is now focusing on renegotiating contracts, cutting costs and ensuring energy supply. Minister Tuku said that even if load shedding decreases, the debt burden will have to be reduced. Priority is being given to uninterrupted supply during Ramadan and the summer season.
However, experts believe that for a long-term solution, it is essential to ensure energy security, increase domestic production, and ensure sustainable contracts. Otherwise, despite the capacity, the people will have to endure both load shedding and debt burden.