❐ BD Digest Desk
Due to coal shortage, the Adani Power plant has been generating electricity on a limited scale for the past month. Later, as coal supply increased, production started increasing from the evening of last Thursday (September 10). However, in the middle of the night, around 12 am, one of the plant’s units was shut down due to a sudden technical glitch. As a result, the power supply has decreased and the level of load shedding has increased across the country.
According to sources from the Power Grid Company and the Power Development Board (PDB), Adani reduced its production from August 7 due to disruption in coal supply due to adverse weather conditions and storms. Later, towards the end of last month, they increased power supply to 900 MW during the day and 1,200 MW from evening to midnight.
Even last night, the amount of electricity generated exceeded 1,400 MW. But due to a unit failure, the overall production has now dropped below 750 MW.
It is worth noting that Adani’s coal-fired power plant in Jharkhand, India, has a total generating capacity of 1,600 MW. Adani signed a power purchase agreement with PDB in 2017. The plant has two units with a capacity of 800 MW, from which there is a record of supplying more than 1,500 MW of electricity when needed.
Two officials at Adani’s power plant said the main problem is in the boiler. It will take at least 48 hours for the faulty part to cool down, after which only the main repair work can be started. As a result, it may take some time for the plant to return to full production.
According to PDB sources, due to the severe gas crisis that has been going on for more than two months, about 1,500 MW of electricity generation has been reduced from gas-based plants. In addition, coal-based power plants are not being operated at full capacity due to coal shortage and mechanical problems.
A unit of the Payra power plant in Patuakhali has been shut down for some time due to mechanical problems, and another unit there is facing a coal shortage. The Rampal power plant in Bagerhat has also been forced to reduce its production due to the same reason, sources said.
According to those concerned, it is not possible to cope with the current situation even by increasing the use of fuel oil and increasing electricity production. As the temperature rises, the intensity of load shedding is increasing.
A record high of 3,557 megawatts of load shedding was seen yesterday at 3 pm. Even today, on a holiday morning, there is a power shortage or load shedding of more than 2,500 megawatts across the country.